NEW QUESTION # 26
Which of the following is NOT required when initially planning a project?
- A. A schedule that identifies tasks required on a project.
- B. Resource Identification and leveling.
- C. The duration of each task.
- D. Logical relationships between the tasks.
Answer: C
NEW QUESTION # 27
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
- A. Certain activities in the critical path have no successors.
- B. The schedule has too much detail to reflect an accurate critical path.
- C. Different calendars are assigned to certain activities in the logical chain.
- D. The schedule is projecting an "early completion".
Answer: A
NEW QUESTION # 28
Determine the driving activity for Activity 10001.
- A. There is no driving activity for Activity 10001 in the backward pass.
- B. Activity 10002.
- C. Activity 9005.
- D. Activity 11001.
Answer: B
NEW QUESTION # 29
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
- A. 09-18-01.
- B. 09-28-01.
- C. 09-15-01.
- D. 09-08-01.
Answer: D
NEW QUESTION # 30
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
- A. The activities run concurrently.
- B. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
- C. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
- D. The activities occur in series with a 15-day lag.
Answer: D
NEW QUESTION # 31
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
- A. 18 work days
- B. 8 work days
- C. 15 workdays
- D. 7 work days
Answer: B
NEW QUESTION # 32
What was the original planned duration for Activity A through Activity G?
- A. 24.
- B. 26.
- C. 28.
- D. 25.
Answer: C
NEW QUESTION # 33
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.
- A. 02-19-04.
- B. EF.11001.
- C. LS.11001 + 25 days.
- D. EF.11001 + 1 day.
Answer: A
NEW QUESTION # 34
An earned value-based project control system can use either of which two budgets as the basis of its calculations?
- A. Linear feet or dollars.
- B. Labor hours or dollars.
- C. Direct or indirect cost.
- D. Earned or budgeted cost yearly.
Answer: D
NEW QUESTION # 35
What is the actual duration as of the status date or data date of Activity B?
- A. 3.
- B. 4.
- C. 7.
- D. 0.
Answer: A
NEW QUESTION # 36
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
- A. 407 days
- B. 255 days
- C. 362 days
- D. 267 days
Answer: A
NEW QUESTION # 37
Total float is defined as the amount of time an activity can be delayed without impacting
- A. The end of that activity
- B. The buoyancy of a successor activity
- C. The overall project completion
- D. The next activity
Answer: C
NEW QUESTION # 38
What is the cycle time?
- A. 17 minutes
- B. 6 minutes
- C. 14 minutes
- D. 5 minutes
Answer: A
NEW QUESTION # 39
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?
- A. 06-18-02.
- B. 06-05-02.
- C. 06-11-02.
- D. 06-04-02.
Answer: B
NEW QUESTION # 40
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?
- A. 12.
- B. Cannot be determined.
- C. 14.
- D. 13.
Answer: A
NEW QUESTION # 41
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?
- A. ADM uses arrows, while PDM uses boxes.
- B. ADM is limited to finish-to-start logic relationships, while PDM is not.
- C. PDM is a bar chart with network logic, while ADM is a pure logic network.
- D. ADM is manual CPM calculations, while PDM is computerized.
Answer: B