NEW QUESTION # 26
Which of the following is NOT required when initially planning a project?

  • A. A schedule that identifies tasks required on a project.
  • B. Resource Identification and leveling.
  • C. The duration of each task.
  • D. Logical relationships between the tasks.

Answer: C


NEW QUESTION # 27
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

  • A. Certain activities in the critical path have no successors.
  • B. The schedule has too much detail to reflect an accurate critical path.
  • C. Different calendars are assigned to certain activities in the logical chain.
  • D. The schedule is projecting an "early completion".

Answer: A


NEW QUESTION # 28
Determine the driving activity for Activity 10001.

  • A. There is no driving activity for Activity 10001 in the backward pass.
  • B. Activity 10002.
  • C. Activity 9005.
  • D. Activity 11001.

Answer: B


NEW QUESTION # 29
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

  • A. 09-18-01.
  • B. 09-28-01.
  • C. 09-15-01.
  • D. 09-08-01.

Answer: D


NEW QUESTION # 30
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

  • A. The activities run concurrently.
  • B. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
  • C. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
  • D. The activities occur in series with a 15-day lag.

Answer: D


NEW QUESTION # 31
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

  • A. 18 work days
  • B. 8 work days
  • C. 15 workdays
  • D. 7 work days

Answer: B


NEW QUESTION # 32
What was the original planned duration for Activity A through Activity G?

  • A. 24.
  • B. 26.
  • C. 28.
  • D. 25.

Answer: C


NEW QUESTION # 33
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

  • A. 02-19-04.
  • B. EF.11001.
  • C. LS.11001 + 25 days.
  • D. EF.11001 + 1 day.

Answer: A


NEW QUESTION # 34
An earned value-based project control system can use either of which two budgets as the basis of its calculations?

  • A. Linear feet or dollars.
  • B. Labor hours or dollars.
  • C. Direct or indirect cost.
  • D. Earned or budgeted cost yearly.

Answer: D


NEW QUESTION # 35
What is the actual duration as of the status date or data date of Activity B?

  • A. 3.
  • B. 4.
  • C. 7.
  • D. 0.

Answer: A


NEW QUESTION # 36
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

  • A. 407 days
  • B. 255 days
  • C. 362 days
  • D. 267 days

Answer: A


NEW QUESTION # 37
Total float is defined as the amount of time an activity can be delayed without impacting

  • A. The end of that activity
  • B. The buoyancy of a successor activity
  • C. The overall project completion
  • D. The next activity

Answer: C


NEW QUESTION # 38
What is the cycle time?

  • A. 17 minutes
  • B. 6 minutes
  • C. 14 minutes
  • D. 5 minutes

Answer: A


NEW QUESTION # 39
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

  • A. 06-18-02.
  • B. 06-05-02.
  • C. 06-11-02.
  • D. 06-04-02.

Answer: B


NEW QUESTION # 40
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

  • A. 12.
  • B. Cannot be determined.
  • C. 14.
  • D. 13.

Answer: A


NEW QUESTION # 41
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

  • A. ADM uses arrows, while PDM uses boxes.
  • B. ADM is limited to finish-to-start logic relationships, while PDM is not.
  • C. PDM is a bar chart with network logic, while ADM is a pure logic network.
  • D. ADM is manual CPM calculations, while PDM is computerized.

Answer: B


NEW QUESTION # 42
......