
Real PRINCE2-Foundation are Uploaded by TestPassKing provide 2024 Latest PRINCE2-Foundation Practice Tests Dumps.
All PRINCE2-Foundation Dumps and PRINCE2 Foundation written Exam Training Courses Help candidates to study and pass the PRINCE2 Foundation written Exam Exams hassle-free!
PRINCE2-Foundation certification exam is globally recognized and provides professionals with a competitive edge in the job market. It demonstrates that the professional has the knowledge and skills required to manage projects using the PRINCE2 methodology. PRINCE2 Foundation written Exam certification exam also provides a common language for project management, which enables professionals to collaborate and communicate effectively in a project environment. Overall, the PRINCE2-Foundation certification exam is a valuable certification for professionals who want to excel in project management.
NEW QUESTION # 87
Which is a purpose of the Project Product Description?
- A. Define the quality anticipated by the customer
- B. Define the key responsibilities for delivering product quality
- C. Provide information about the state of products
- D. Provide product cost input to the Business Case
Answer: A
NEW QUESTION # 88
Which statement about the Directing a Project process is FALSE?
- A. Covers the day-to-day activities of the Project Manager
- B. Supports the PRINCE2 principle of manage by exception
- C. Is triggered by a request to initiate a project
- D. Provides a mechanism for the Project Board to assure that there is continued business justification
Answer: A
NEW QUESTION # 89
Which is a purpose of a Project Brief?
- A. Capture lessons from previous projects
- B. Define the quality techniques and standards to be applied during the project
- C. Ensure that there is a common understanding of the starting point for the project
- D. Confirm that the Project Plan is able to deliver the Business Case
Answer: C
NEW QUESTION # 90
Which is part of quality control?
- A. Documenting the customer's quality expectations
- B. Providing assurance that the project is being conducted properly
- C. Writing product descriptions
- D. Undertaking quality reviews
Answer: D
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Quality#Part_2:_Quality_Control_Introduction
NEW QUESTION # 91
Which is a purpose of the 'controlling a stage' process?
- A. To update a project plan to incorporate the actuals from a stage plan
- B. To select and implement actions that will resolve deviations from a plan within tolerance
- C. To obtain approvals for products delivered in a work package
- D. To produce a team plan for the work to be assigned to a team manager
Answer: B
Explanation:
Reference http://prince2.wiki/Controlling_a_Stage#Purpose
NEW QUESTION # 92
Which task is performed by the Change Authority?
- A. Set a change budget
- B. Refer changes that exceed budgetary limits to the Project Manager for approval
- C. Approve or reject a request for change within approved limits
- D. Update the configuration management system whena change is approved
Answer: C
NEW QUESTION # 93
Which is an objective of the 'managing a product delivery' process?
- A. To assess whether the stage products have been approved
- B. To ensure the business case is regularly reviewed
- C. To request authorization to start the next stage
- D. To deliver the planned specialist products within tolerance
Answer: D
Explanation:
Explanation
Reference http://prince2.wiki/Managing_Product_Delivery#Objective
NEW QUESTION # 94
Which process monitors work that has been assigned to a team manager?
- A. Controlling a stage
- B. Managing product delivery
- C. Managing a stage boundary
- D. Directing a project
Answer: B
Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-process-managing-product-delivery.php
NEW QUESTION # 95
Which is one of the six aspects of project performance that needs to be managed?
- A. Risk
- B. Security
- C. Change
- D. Progress
Answer: A
Explanation:
Section: Volume A
NEW QUESTION # 96
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.
- A. and the project board are responsible
- B. and the team manager(s) are accountable
- C. decides who is responsible
- D. has responsibility
Answer: D
Explanation:
Explanation
Reference http://prince2.wiki/Directing_a_Project
NEW QUESTION # 97
Which is a purpose of an End Project Report?
- A. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
- B. Ensure that key project information is archived and made secure
- C. Identify individuals or groups that need to be told that the project is coming to an end
- D. Review how well the project performed against the Project Initiation Documentation used to authorize it
Answer: D
NEW QUESTION # 98
Which is an objective of the quality review technique?
- A. To provide a common understanding of what products a project will create
- B. To define the quality methods required within a project
- C. To baseline a product
- D. To determine the quality responsibilities of a project team
Answer: C
NEW QUESTION # 99
What takes place during the Closing a Project process?
- A. Ownership of the project's products is transferred to the customer
- B. The post-project benefits reviews are performed
- C. The project closure notification is reviewed and approved
- D. An End Stage Report is prepared for the final stage
Answer: A
Explanation:
Section: Volume A
NEW QUESTION # 100
Which role is responsible for the management of a risk assigned to it?
- A. Risk actionee
- B. ProjectSupport
- C. Risk owner
- D. Project Assurance
Answer: C
NEW QUESTION # 101
Which is a purpose of the quality theme?
- A. To enable the project to be managed according to plan
- B. To check that the project is viable and achievable
- C. To ensure that formal issues are recorded
- D. To ensure that the project outputs are agreed
Answer: B
Explanation:
Section: Volume B
Explanation/Reference:
NEW QUESTION # 102
......
Valid Way To Pass PRINCE2's PRINCE2-Foundation Exam with : https://passleader.testpassking.com/PRINCE2-Foundation-exam-testking-pass.html